In order to calculate the Total factory overhead costs: -
We Know,
- Predetermined Factory Overhead Rate = Â Total Factory Overhead Costs / Direct Labor Hours
- Factory overheads applied to Job 305 =  Predetermined overhead rate × Direct labor hours
Statement showing Computations
- Particulars                              Amount
  a)
- Estimated total factory overhead costs     620,000.00
- Direct labor hours                        80,000.00 Â
- Predetermined factory overhead rate
- = 620,000 / 80,000 Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â 7.75
  b)
- Factory overhead applied to Job 200 Â Â Â Â Â
- = 2500 × 7.75                            19,375.00
- Factory overhead applied to Job 305
- = 3000 × 7.75                            23,250.00 Â
JOURNAL ENTRY Â Â Â Â Â Â Â Â Â Â Â Â Â Â Dr. Â Â Â Â Â Â Â Â Â Â Â Cr.
Work in Process Dr. Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â Â 42,625.00 Â
To Factory Overhead                               42,625.00
Therefore, Total factory overhead cost is 42,625.00.