Answer:
$1,652,400
Explanation:
Given that;
Projections for the month = 30,600 units
Direct labor time = 3 hours per unit
Labor cost per hour = $18
Then, Total budgeted direct labor cost for May would be;
= Projections for the month Ă— Direct labor time Ă— labor cost per hour
= 30,600 Ă— 3 Ă— $18
= $1,652,400