A contractor decides that he can build a barn in nine weeks using four men. If he employs two more men, how long will the job take? Assume that all the men work at the same rate.

Relax

Respuesta :

Answer: 6weeks

Step-by-step explanation:

If it takes 4 men, 9 weeks to build a barn.

It will take a man; 4 x 9weeks =36 weeks to make a barn

If it takes a man 36weeks to make a barn, it will take 4men + 2 men i.e 6men = 36/6

6 weeks to make a barn

The long will the job take:

  • If it takes 4 men, 9 weeks to build a barn.
  • It will take a man; 4 x 9weeks =36 weeks to make a barn
  • If it takes a man 36weeks to make a barn, it will take 4men + 2 men i.e 6men = 36/6

Thus,by adding two more men it will take 6 weeks to make a barn.