which of the following statement is correct? a. Process group is the same as project phases, b. each process group has a mapped project phase, c. process group are not project phases, d. the monitoring and control process group applies only in the monitoring and control phase

Relax

Respuesta :

Answer:

The answer is C

Project groups are NOT project phases.