Answer:
$ 116,176
Explanation:
Given:
Direct labor hours required by each unit = 0.70
Direct labor rate = $ 10.60 per direct labor-hour
Number of units to be produced in April = 7,600 units
Number of units to be produced in May = 7,400 units
Minimum labor hours per month for which the labor is paid = 5,480 hours
Now,
Labor hour for the month of April
= Number of units to be produced in April × Direct labor hours required
= 7,600 × 0.70
Labor hour for the month of April = 5320 hours
and,
Labor hour for the month of May
= Number of units to be produced in May × Direct labor hours required
= 7,400 × 0.70
Labor hour for the month of April = 5180 hours
since, the direct labor hour hour required each month is less than the minimum labor hour for which the labors will be paid i.e 5,480 hours
thus,
The total direct labor cost for 2 months will be
= (Number of Units for April + Number of Units for May ) × Labor Rate
or
= (5480 + 5480) × $ 10.60
or
The total direct labor cost for 2 months = $ 116,176