A new product is released. when a customer identifies performance issues with this product, the project manager realizes that cost of quality (coq) should have been used to estimate this cost. which category of coq should the project manager have used?
A prevention costs
B external failure costs
C appraisal costs
D cost-benefit analysis

Relax

Respuesta :

Otras preguntas

Why does a closed system allow for more reliable measurements than an open system when observing a chemical reaction? A closed system conserves all of the produ
how do you find averge speed?
In your own words, describe how matter is identified.
why is the sky sometimes red???
1.what are the common misinformation about preventing coronavirus?​
Two angles form a linear pair. The measure of one angle is (4y + 54)∘and the other angle is (2y + 90)∘. Find the measures of each angle. Do not include any unit
what is the median of the numbers given below? 2,2,8,10,15,30,36,40,50,51 Report your answer in decimal form.
[tex]x^{2} -10x+5-3(x-5)[/tex] phân tích đa thức
how do scientist know about the interior of the earth?​
List some foods that you eat regularly. How much do you think you spend on food a month?