The _____ for an activity is the latest possible time an activity might begin without delaying the project finish date. Group of answer choices early finish date late finish date late start date early start date

Relax

Respuesta :

Answer:

Late start date.

Explanation:

The late start date is the latest possible time an activity might begin without delaying the project finish date. It takes into account both parts of the sentences. "Late" as in "latest possible time", and start as in "[to] being, without delaying the project...".